The construction of the Ondangwa Sports Stadium is progressing steadily, with the latest focus on the drainage system and power station, among other key areas.

Among the crucial construction elements at the Ondangwa stadium is the drainage system, which is being prioritized to expedite the planting of the field grass. 

This is essential for hosting sporting events at the stadium in the near future.

Other significant developments, including the stadium leveling, ticket booth, and power station, are also underway to ensure timely completion of these vital components.

Ondangwa Town Council Manager of Infrastructure, Planning, and Technical Service, Petrus Shipanga, provided updates on the project at the stadium site. 

Shipanga emphasized the Ondangwa Town Council's commitment to completing the stadium to the highest standards, ensuring the project's quality.

The multimillion-dollar Ondangwa stadium project is anticipated to be completed within the next five years, with an estimated cost of N$240 million

-