New contractor for Swakop Neonatal Unit shows progress
Breadcrumb
The new contractor for the Neonatal Unit at Swakopmund Hospital is aiming to complete construction by August 26 this year.
The N$26 million project has faced delays over the years, which led to the termination of the tender initially awarded to Shatty Construction.
The Ministry of Health and Social Services says Shatty Construction got the tender in November 2020.
But the company, which is an SME, failed to complete the project in February 2022 as agreed, despite the government allegedly paying the SME.